Cabinet approves Revised Cost Estimate of Dam rehabilitation and Improvement Project

19-9-2018
  • Contents

The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, has approved the Revised Cost Estimate of Dam Rehabilitation and Improvement Project (DRIP) at the revised cost of ₹ 3466 crore with the financial assistance of the World Bank to improve safety and operational performance of 198 Dams, along with institutional strengthening with system wide management approach.  Out of ₹ 3,466 crore, ₹ 2,628 crore will be funded by the World Bank and ₹ 747 crore will be funded by DRIP States / Implementing Agencies (IAs) and balance ₹ 91 crore to be funded by Central Water Commission (CWC).

 The CCEA also gave its ex-post facto approval for two-year time extension from 1st July, 2018 to 30th  June, 2020

Impact:

The project will improve the safety and operational performance of selected existing dams and mitigate risks to ensure safety of downstream population and property.  The primary beneficiaries are both urban and rural communities dependent on reservoir and downstream communities, who are prone to risk associated with dam failure or operational failure.  Further, through institutional strengthening component, effectiveness of Dam Safety Organisations will be increased to take the lead to make dams safe from structural and operational point of view through capacity building of staff and officials.

Details:

DRIP envisages following objectives: -

a)   Component-I: - Rehabilitation of Dam and its Appurtenant Structures,

b)   Component-II: - Institutional Strengthening and

c)   Component-Ill: - Project Management.

The Scheme envisages comprehensive rehabilitation of 198 existing dam projects located in seven states of India namely, Kerala, Madhya Pradesh, Odisha, Tamil Nadu, Karnataka, Jharkhand (Damodar Valley Corporation) and Uttarakhand (Uttarakhand Jal Vidyut Nigam Limited).

Numbers of dams with initial and revised cost submitted by Implementing Agencies are as follows:

Implementing Agency

 

No. of Project Dams

Total Initial Project Cost ( Rs Crore)

Total Project Revised Cost ( Rs Crore)

Madhya Pradesh WRD

25

315

169

Odisha WRD

26

148

751

Tamil Nadu WRD

69

486

543

TANGEDCO

20

260

260

Kerala WRD

16

158

360

KSEB

12

122

154

CWC

 

 

132

270

Karnataka WRD

22

276

581

UJVNL

5

64

235

DVC

3

139

143

Total Cost (in Rs Crore)

198

2100

3466

Background:

Originally, the total cost of DRIP was ₹ 2100 Crore with State component of ₹ 1968 Crore and Central Component of ₹ 132 Crore. Initially the project was a six-year Project which commenced on 18th April, 2012 with a scheduled closing on 30th June, 2018. The Project implementation has been granted in-principle approval for two years extension in the year 2017 by Union Minister of Water Resources, River Development and Ganga Rejuvenation and the World Bank with a revised closure date of the project by 30th June 2020.