Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

TMI Blog

Home

1988 (4) TMI 429

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... d into sometime in 1972. It is stated that all the four contracts were executed and completed by the first respondent on diverse dates. The last one was on 30th May, 1971. Between 29th May, 1972 to 19th June, 1972, the respondent accepted the four final bills and gave no claim declaration in respect of the four contracts. The respondent wrote a letter to the Additional Chief Engineer, R.E.N.R. Allahabad, stating that Rs.1,91,137 were due on account of the work executed and requested him to refer the dispute to the Arbitrator. On 4th June, 1976 a reply was sent to the above letter stating that there was no dispute between the parties and, hence, no question of appointment of any Arbitrator arose. On 13th December, 1976, an application was fi .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... orests of Chamba District. The period of agreement was one year from September 1, 1960. Under an arbitration clause in the agreement all disputes between the parties were to be referred to the Deputy Commissioner, Mandi District Himachal Pradesh. The second appellant transferred all his rights under the agreement to the first appellant with the consent of the State of Himachal Pradesh. Disputes arose between the parties in October, 1950. On May 30, 1952 the appellants addressed a letter to the Chief Conservator of Forests, Himachal Pradesh requiring that officer to submit the matters in difference to the arbitration of the Deputy Commissioner, Mandi Distt. By a letter dated June 23, 1952, the Chief Conservator declined to agree to a referen .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... interpreted as so restricted. In the aforesaid background this Court directed the arbitration agreement to be filed. This question was again considered by this Court in Mohd. Usman Military Contractor, Jhansi v. Union of India, Ministry of Defence, [1969] 2 SCR 233. There the appellant had entered into a contract with the Government of India. The contract contained an arbitration clause. For certain supplies made under the contract the appellant made representations to the Government for payment and for arbitration of disputes. On or about July 10, 1958 Government refused to refer the matter for arbitration. On July 11, 1961 the appellant filed an application in the Court of District Judge under Sections 8 & 20 of the Act, for filing the .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... r the Arbitration Act but no similar change was made in Article 181. It was manifest that save as provided in Articles 158 & 178 there would not be any limitation for other application. In the circumstances the Court found it impossible to construe the implied reference in Article 181 as a reference to the Arbitration Act, or to hold that Article 181 applied to applications under that Act. In the premises the Court held that an application under Sections 8 & 20 of the Arbitration Act, 1940 was not governed by Article 181 of the Limitation Act. In that view of the matter the application was held to be barred by limitation. The question is now concluded as mentioned hereinbefore vide this Court's decision in Kerala State Electricity Board .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... e purpose of getting an arbitrator appointed, a letter dated June 4, 1976 was sent by the appellant to the Additional Chief Engineer, Allahabad. The respondent did not take any step in time. The appellant filed an application on 4.6.1976 under Section 20 of the Act. It was contended before the learned Trial Judge that the work under all the four contracts had been fully executed by the appellant on different dates and the respondents claimed that the appellant had accepted full and final payment of the agreements which had been executed by it and no claim declaration in respect of the same had been given by the appellant. It was, therefore, submitted that since there was no dispute, the application filed under Section 20 of the Act, was mis .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

 

 

 

 

Quick Updates:Latest Updates