2011 (8) TMI 1061 - AT - Income TaxDeduction u/s 80IB(10) - delay in obtaining the completion certificate - Held that:- Date that appear on the Architect's Completion certificate filed before the local authority is a relevant one. In the instant case, the said date is 25-3-2008 and the assessee filed requisite form before the local authorities intimating the completion of the project. The said certificate/ intimation was accepted by the local authority without any amendments or objections. Local authority has not raised any queries on the quality construction of the building or the completion of the same as per the plans approved by such authority. Delay in obtaining the completion certificate on 10-10-2008 is certainly not attributable to the assessee and obtaining the said certificate before 31.3.2008 is beyond the control of the assessee. Assessee's job includes the completion of the building in accordance with the approved plans and intimation of the same to the local authority by way of filing the requisite Forms together with the Completion certificate given by the Architect, the specialist in the matter and the assessee has done his job scrupulously in this case. However, the local authority has neither objected to the said application of the assessee and the Architect by raising any objections nor accepted by issue of said completion certificate till 10.10.2008. Therefore, the delay in grant of the said certificate is certainly not attributable to the assessee. Therefore, in our opinion, the assessee is not defaulter on this account and thus, the AO has erred in denying the deduction u/s 80IA(10)- Decided in favour of assessee.
|