2020 (3) TMI 1400 - Tri - Insolvency and BankruptcyWithdrawal of auction notices - seal and detach the projects site - HELD THAT:- As per the submission of the counsel for the Resolution Professional the claim has been admitted. In spite of that the property has not been released from the attachment and notices were issued for auction of the property by the said Authority - It is on record that in the present matter CIRP has been initiated against JNC Construction Private Limited on 30.05.2019 and the moratorium was declared. The Interim Resolution Professional has made efforts to seek the detachment of the property and to take the possession of the same but till date the possession has not been given by the said authority. List on 30.03.2020.
|