Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases Indian Laws Indian Laws + SC Indian Laws - 2024 (1) TMI SC This

  • Login
  • Cases Cited
  • Referred In
  • Summary

Forgot password       New User/ Regiser

⇒ Register to get Live Demo



 

2024 (1) TMI 1459 - SC - Indian Laws


Issues Presented and Considered

1. Whether the writ petition filed by the bidder challenging the procurement process and seeking a mandamus for issuance of Letter of Intent and execution of Power Purchase Agreement was maintainable before the High Court under Article 226 of the Constitution, given the existence of alternate remedies under the Electricity Act, 2003.

2. Whether the State Commission and the Bid Evaluation Committee (BEC) have the power to reject bids or refuse to adopt tariffs that are not aligned with prevailing market prices, notwithstanding that the tariff was determined through a transparent competitive bidding process under Section 63 of the Electricity Act.

3. Whether the procurers (distribution licensees) are obligated to purchase electricity from all "successful bidders" down the ranking order ("filling the bucket") up to the total required quantum, irrespective of the tariffs quoted by the bidders.

4. The scope and interpretation of Section 63 of the Electricity Act, 2003, particularly the power of the Appropriate Commission to "adopt" tariffs determined through competitive bidding and the extent of regulatory oversight over such tariffs.

5. The legal effect and interpretation of the term "successful bidder" as defined in the Request for Proposal (RFP) and whether a bidder who was not issued a Letter of Intent (LoI) can be considered a successful bidder entitled to supply power.

6. The applicability and interpretation of clauses in the RFP and the Central Government's Competitive Bidding Guidelines, especially Clause 5.15 which empowers the evaluation committee to reject all price bids if tariffs are not market aligned.

7. Whether the High Court erred in issuing a mandamus directing the State instrumentalities to purchase power from the bidder at the quoted tariff, without regard to consumer interest and the regulatory framework.

8. The impact of delay and laches by the bidder in asserting its claim.

Issue-wise Detailed Analysis

1. Maintainability of Writ Petition under Article 226

Legal Framework and Precedents: The Electricity Act, 2003 is a complete code governing electricity matters, with designated forums such as the State Electricity Regulatory Commission (SERC) and the Appellate Tribunal for Electricity (APTEL) for adjudication of disputes. The Supreme Court in PTC India Limited v. CERC held that the Act provides exhaustive remedies and the High Courts should not entertain writ petitions where efficacious statutory remedies exist.

Court's Reasoning: The Court held that the writ petition was not maintainable as the petitioner had alternate remedies before the State Commission and APTEL. The petitioner had delayed for years before approaching the High Court, and the High Court erred in exercising writ jurisdiction in the presence of adequate alternate remedies.

Conclusion: The writ petition was barred on grounds of maintainability and delay. The High Court should have declined jurisdiction.

2. Power of State Commission and BEC to Reject Non-Market Aligned Tariffs

Legal Framework and Precedents: Section 63 of the Electricity Act mandates the Appropriate Commission to adopt tariffs determined through a transparent bidding process in accordance with Central Government guidelines. The Competitive Bidding Guidelines (2005) Clause 5.15 empowers the evaluation committee to reject all price bids if rates are not aligned to prevailing market prices. The Court in Energy Watchdog v. CERC and Tata Power Transmission v. MERC clarified that the Commission's power to adopt tariff is not mechanical and it can scrutinize compliance with guidelines and market alignment.

Court's Reasoning: The Court emphasized that the State Commission is not a mere post office. It has regulatory powers under Section 86(1)(b) to regulate electricity purchase and prices. The BEC, comprising technical and financial experts, found the tariffs of certain bidders (including the petitioner) exorbitant and not market aligned, which was upheld by the State Commission. The APTEL erred in reversing this well-reasoned decision.

Application of Law to Facts: The petitioner's tariff was higher than other bidders and recent market bids. Accepting such tariffs would impose an undue financial burden on consumers, violating consumer interest and public policy.

Conclusion: The State Commission and BEC have the power and duty to reject bids not aligned with market prices, and the adoption of tariffs must consider consumer interest.

3. Obligation to Purchase from All Successful Bidders ("Filling the Bucket")

Legal Framework: The RFP clauses 3.5.3 to 3.5.6 describe the selection of successful bidders in ascending order of tariff until the requisitioned capacity is met. Clause 3.5.12 allows rejection of bids if tariffs are not market aligned. "Successful bidder" is defined as one to whom a LoI has been issued.

Court's Reasoning: The Court rejected the theory that procurers must compulsorily purchase power from all bidders down the ladder irrespective of tariff. The "filling the bucket" theory lacks basis in the RFP and guidelines. The procurer has discretion to reject bids with exorbitant tariffs to protect consumer interest. The Court cautioned against forcing procurers to accept bids with tariffs far above market rates, which would be detrimental to consumers and public interest.

Conclusion: Procurers are not bound to accept all bids merely to meet quantum; bids must be market aligned, and procurers have discretion to reject exorbitant bids.

4. Interpretation of Section 63 of the Electricity Act

Legal Framework and Precedents: Section 63 mandates adoption, not determination, of tariff by the Appropriate Commission if determined through transparent bidding per Central Government guidelines. The Commission's power to regulate tariff under Section 79(1)(b) and Section 86(1)(b) remains intact and must be harmonized with Section 63.

Court's Reasoning: The Court emphasized a holistic reading of the Act, holding that the Commission's regulatory powers include scrutiny of tariff alignment with guidelines and market conditions. The Commission cannot abdicate its regulatory role by blindly adopting tariffs without scrutiny.

Conclusion: The Commission must adopt tariffs only if bidding is transparent and tariffs are market aligned, exercising regulatory powers consistent with the Act.

5. Definition and Legal Status of "Successful Bidder"

Legal Framework: The RFP defines "successful bidder" as one selected by the procurer and issued a LoI. No LoI means no successful bidder status.

Court's Reasoning: Since the petitioner was not issued a LoI and its bid was returned, it cannot be considered a successful bidder entitled to supply power or claim contractual rights.

Conclusion: The petitioner is not a successful bidder under the RFP and has no vested right to contract or supply power.

6. Interpretation of Clauses in RFP and Bidding Guidelines

Legal Framework: Clauses 2.15.1 and 3.5.12 of the RFP and Clause 5.15 of the Bidding Guidelines empower the procurer/BEC to reject bids not aligned to market prices without liability.

Court's Reasoning: The Court held that these clauses confer discretion to reject bids individually or collectively if tariffs are exorbitant. The power is not limited to rejecting all bids only if the entire bidding process is flawed but extends to selective rejection of bids to protect consumer interest.

Conclusion: The procurer and BEC have the discretion to reject bids with non-market aligned tariffs, consistent with the guidelines and RFP.

7. Legality of High Court's Mandamus to Procure Power at Quoted Tariff

Legal Framework and Precedents: The Court in Air India Ltd. v. Cochin International Airport Ltd. held that contract awards are commercial decisions subject to adherence to norms but not judicial scrutiny of commercial merits unless mala fide or arbitrary.

Court's Reasoning: The mandamus directing procurement at petitioner's tariff ignored consumer interest and regulatory framework. The decision-making process by BEC and State Commission was lawful and rational. The High Court's interference was unwarranted and contrary to public interest.

Conclusion: The High Court erred in issuing mandamus compelling procurement at disputed tariff, and such interference is not justified absent arbitrariness or mala fides.

8. Delay and Laches

Court's Reasoning: The petitioner delayed for years before asserting its claim, acquiescing in the rejection of its bid and non-renewal of bid bond. Delay and laches are relevant in discretionary relief. The petitioner failed to justify the delay adequately.

Conclusion: Delay and laches further disentitled the petitioner from relief.

Significant Holdings

"The appropriate Commission does not act as a mere post office Under Section 63. It must adopt the tariff which has been determined through a transparent process of bidding, but this can only be done in accordance with the guidelines issued by the Central Government."

"The evaluation committee shall have the right to reject all price bids if the rates quoted are not aligned to the prevailing market prices."

"The State Commission and the Bid Evaluation Committee have the power and duty to consider consumer interest and reject bids which are exorbitant and not market aligned."

"The procurer is not bound to accept bids from all bidders merely to fill the requisitioned capacity if such bids are exorbitant and not aligned to market prices."

"The writ petition was not maintainable before the High Court in presence of efficacious statutory remedies under the Electricity Act."

"The High Court erred in issuing mandamus directing procurement at disputed tariff, ignoring the regulatory framework and consumer interest."

"Delay and laches in asserting rights under the bidding process disentitle the petitioner from relief."

"The word 'any' in statutory provisions must be construed in context and can mean 'all' depending on the scheme and object of the legislation."

"The State Commission's power to regulate electricity purchase and prices under Section 86(1)(b) includes scrutiny of tariffs adopted under Section 63."

 

 

 

 

Quick Updates:Latest Updates