Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding

🚨 Important Update for Our Users

We are transitioning to our new and improved portal - www.taxtmi.com - for a better experience.

⚠️ This portal will be discontinued on 31-07-2025

If you encounter any issues or problems while using the new portal,
please let us know via our feedback form so we can address them promptly.

  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

Home Case Index All Cases IBC IBC + AT IBC - 2025 (6) TMI AT This

  • Login
  • Summary

Forgot password



 

2025 (6) TMI 460 - AT - IBC


The Appeals arise from the Corporate Insolvency Resolution Process (CIRP) of the Corporate Debtor, involving multiple Financial Creditors and the Resolution Professional (RP). The core issues relate to the classification and admission of claims of certain creditors, the status of these creditors as secured or unsecured, the propriety of the RP's conduct and decisions, and procedural fairness in the adjudication of claims and replacement of the RP.

Issues Presented and Considered:

The Tribunal identified the following key issues for determination:

I. Whether Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. qualify as Financial Creditors of the Corporate Debtor.

II. Whether Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. are Secured Financial Creditors by virtue of the MoU dated 26.12.2009 and deposit of title deeds with an escrow agent.

III. Whether the Adjudicating Authority's order awarding 18% interest to Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. is sustainable.

IV. Whether the Adjudicating Authority erred in reducing the claim of Arrow Engineering Ltd. without affording it an opportunity to be heard.

V. Whether adverse observations against the Central Bank of India regarding inflated claims are sustainable, especially when Central Bank was not a party to the relevant proceedings.

VI. Whether the Adjudicating Authority rightly exercised jurisdiction in directing replacement of the Resolution Professional and whether sufficient material existed for adverse observations against the RP.

VII. Whether the direction for a detailed forensic audit by KPMG was justified.

VIII. Whether Shree Ram Vessel Scrap Pvt. Ltd. made out a case for interference with directions restricting fresh resolution plans.

IX. Reliefs to which the appellants are entitled.

Issue-wise Detailed Analysis:

Issue I: Status of Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. as Financial Creditors

The MoU dated 26.12.2009 between the Corporate Debtor and these entities involved advances of Rs.132 Crores, with a provision for refund with 18% interest if the joint development agreement was not executed. The Adjudicating Authority, in its order dated 16.03.2023, held that these advances acquired the character of financial debt under Section 5(7) and 5(8) of the Insolvency and Bankruptcy Code (IBC), 2016. The RP admitted their claims as Financial Creditors accordingly.

Arrow Engineering Ltd. contended that the order was passed without hearing them and challenged the status, but their application for impleadment was rejected and the order was not appealed. The Tribunal held that the order declaring Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. as Financial Creditors had attained finality and could not be reopened in these appeals. The CIRP process being time-bound, finality in such determinations is essential.

Conclusion: Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. are Financial Creditors of the Corporate Debtor, and this status is final.

Issue II: Whether Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. are Secured Financial Creditors

They claimed security interest by way of mortgage created through deposit of title deeds with an escrow agent, as per the letter dated 26.12.2009. The RP rejected the claim of security on grounds that:

  • The alleged mortgage was not registered under the Companies Act, rendering it void.
  • The deposit of title deeds was with an escrow agent, not the creditor, and was intended only to hold documents pending completion of obligations.
  • The Corporate Debtor denied any intention to create a mortgage.
  • The MoU and related documents were declared void by the Supreme Court as violating the Rehabilitation Scheme sanctioned by BIFR.

The Tribunal analyzed the legal framework under Section 58(f) of the Transfer of Property Act, 1882, which recognizes mortgage by deposit of title deeds with intent to create security. It emphasized that intent is crucial. The letter and surrounding circumstances showed the deposit was for escrow purposes, not to create mortgage. The Supreme Court's prior judgment declared the MoU void and without legal force, negating any rights under it.

Reliance on precedent judgments clarified that if parties reduce their bargain to writing, such document requires registration to create a charge. Here, the MoU was unregistered and void.

Conclusion: Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. do not hold any security interest or mortgage rights and are not Secured Financial Creditors.

Issue III: Entitlement to Interest @18%

The Adjudicating Authority awarded interest @18% per annum to Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. Arrow Engineering Ltd. challenged this on the ground that the MoU was void and interest was payable only if the MoU was terminated by the developers, which was not the case.

The Tribunal noted that despite the MoU being void, the financial transaction of Rs.132 Crores advanced remains a financial debt. The Corporate Debtor's own balance sheets acknowledged the debt and the obligation to refund with interest. The MoU's clause 17 provided for reasonable construction of void provisions to achieve parties' intentions. The Corporate Debtor's reply in arbitration proceedings accepted liability to refund with interest.

Conclusion: The award of interest @18% per annum to Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. is sustainable.

Issue IV: Reduction of Arrow Engineering Ltd.'s Claim Without Hearing

The RP admitted Arrow Engineering's claim at Rs.265 Crores, but the Adjudicating Authority reduced it to Rs.40.75 Crores without hearing Arrow Engineering. Arrow Engineering's application for impleadment in the relevant IA was rejected, denying it opportunity to present its case.

The Tribunal held that such reduction without hearing violates principles of natural justice. Pending applications challenging Arrow Engineering's claim remain undecided, and the Adjudicating Authority's order restricting the claim is set aside without prejudice to merits.

Conclusion: The reduction of Arrow Engineering Ltd.'s claim without hearing is unsustainable and set aside.

Issue V: Adverse Observations Against Central Bank of India

The Adjudicating Authority observed that the RP admitted an inflated claim of Central Bank of India and directed re-examination. However, Central Bank was neither party nor heard in the relevant proceedings.

The Tribunal held that such adverse observations without opportunity to be heard are unsustainable. Pending applications challenging Central Bank's claim remain to be decided independently.

Conclusion: Observations against Central Bank of India are set aside for violation of natural justice.

Issue VI: Replacement of Resolution Professional and Adverse Observations

The Adjudicating Authority replaced the RP citing his alleged acceptance of inflated claims and failure to admit certain claims. The RP contended that no procedural requirements under Section 27 of IBC for removal were followed and that no evidence of bias or collusion was produced.

The Tribunal recognized that while the Adjudicating Authority has jurisdiction under Rule 11 of NCLT Rules and Section 60(5) of IBC to replace the RP in appropriate cases, the grounds relied upon here were unfounded and adverse observations were unsubstantiated. The IBBI's advisory on non-disclosure of past employment was not a sufficient basis for removal.

The Tribunal relied on precedents confirming the Adjudicating Authority's power to replace the RP but emphasized that the power must be exercised on proper grounds.

Conclusion: The order directing replacement of the RP is set aside; the RP's removal lacked sufficient foundation.

Issue VII: Direction for Forensic Audit

The Adjudicating Authority ordered a forensic audit by KPMG despite no stakeholder requesting it and the issues before the Authority being limited to claim classification and quantum.

The Tribunal held that such direction was unwarranted and would further delay the CIRP, which was already extended and delayed. The forensic audit was not germane to the issues under consideration.

Conclusion: Direction for forensic audit is set aside as unnecessary and prejudicial to timely completion of CIRP.

Issue VIII: Relief Sought by Shree Ram Vessel Scrap Pvt. Ltd.

The Appellant sought permission to submit a resolution plan after the deadline. The RP and CoC had refused extension of time.

The Tribunal observed that the Appellant failed to submit the plan within the prescribed timeline and that applications seeking extension or fresh invitation were pending. The Tribunal did not interfere with the Adjudicating Authority's directions but left the Appellant free to pursue pending applications.

Conclusion: No interference granted; pending applications to be decided by the Adjudicating Authority.

Issue IX: Reliefs to Appellants

The Tribunal's final directions included:

  • Dismissing appeals challenging denial of secured creditor status to Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd.
  • Allowing appeals filed by the RP, setting aside the order replacing him and restoring him as RP; directing handover of records from the interim RP.
  • Setting aside the order reducing Arrow Engineering Ltd.'s claim.
  • Directing the Adjudicating Authority to decide pending applications challenging claims of Arrow Engineering Ltd. and Central Bank of India within 60 days.
  • Deleting adverse observations against Central Bank of India.
  • Dismissing appeal by Shree Ram Vessel Scrap Pvt. Ltd. with liberty to pursue pending applications.
  • Setting aside the direction for forensic audit.
  • Directing reconstitution of CoC and continuation of CIRP within two months after decision on pending applications.
  • Excluding the period of interim stay from the CIRP timeline and extending CIRP till 17.10.2025.
  • Parties to bear their own costs.

Significant Holdings:

"The order dated 16.03.2023 declaring Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. as Financial Creditors having become final, the said question cannot be allowed to be raised in these Appeals."

"Looking at the anvil of Section 58(f), intent on the part of the Corporate Debtor to create a mortgage by deposit of title is not reflected in the transaction."

"The Hon'ble Supreme Court has specifically held that no right shall accrue to the Suraksha Realty Ltd. and Sheth Developers Pvt. Ltd. on the basis of the MoU dated 26.12.2009."

"The grant of interest @ 18% per annum is sustainable as the financial transaction remains valid despite the MoU being void."

"Reduction of Arrow Engineering Ltd.'s claim without hearing violates principles of natural justice and is set aside."

"Adverse observations against Central Bank of India without hearing are unsustainable and set aside."

"The Adjudicating Authority has jurisdiction to replace the Resolution Professional but the grounds must be sufficient and substantiated; here the replacement was unwarranted."

"Direction for forensic audit was unnecessary and prejudicial to timely completion of CIRP."

"The CIRP process shall be completed within two months after decision on pending applications, with the period of interim stay excluded, and extended till 17.10.2025."

 

 

 

 

Quick Updates:Latest Updates