Dear sir Q-1 , we are manufacturing heavy machenery under chapter 84 , and also work in EPC project my question is we want to shifting DG set from Ahmedabad to Bhatinga for our project site and thereafter finish the project come back from Bhatinda to Ahmedabad, what is the procedure Q-1 We send same Steel Plates at our project site from Ahmedabad to Bhatinda and this plates not came back from Bhatinda to Ahmedabad what is the procedure With Regards Hitendra Dave Posts / Replies Showing Replies 1 to 2 of 2 Records Page: 1
Q1- DG Sets Transfer to the site --- DG sets is fallow under capital goods as per Cenvat Credit Rule, 2004,You can transfer under challan 4(5)(b) Q2- Steel Plates ------ From your question it is not clear were is the use of these steel plates ,or it is your raw material it is better to you discharge the duty while clearing these plates under the cost +10% mark up AMIT
DG set canbe sent without payment of duty on a challan and it should be come back within 180days. Steel plate can be removed on payment of duty or on reversal of equivalent CENVAT credit or on Cost + 10% (as the case may be). Page: 1 Old Query - New Comments are closed. |
||||