Tax Management India. Com
Law and Practice  :  Digital eBook
Research is most exciting & rewarding
  TMI - Tax Management India. Com
Follow us:
  Facebook   Twitter   Linkedin   Telegram

TMI Blog

Home

2016 (4) TMI 801

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... convenience, the facts leading to the filing of FAO (OS) 588 of 2013 are dealt with in detail. 2. Contract No.TNHP/2, Construction Package II-C for a contract price of Rs. 295.53 crores for executing the work of 4-laning and strengthening of the existing 2 lanes sections between km 38 to km 115 on National Highway- 2 in Uttar Pradesh was awarded to the Respondent on 12.03.2001. 3. Clause 14.3 of "Instruction to Bidder" was as under:- "All duties, taxes and other levies payable by the Contractor under the contract, or for any other cause, as of the date 28 days prior to the deadline for submission of bids, shall be included in the rates and prices and the total Bid Price submitted by the bidder." The parties adopted FIDIC form of condi .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... 4. Disputes having arisen between the parties, the matter was referred to the Arbitral Tribunal. Two claims were raised by the respondent namely: "(i) Dispute No. 1 Compensation for additional cost on account of increase in Service Tax on the Insurance Premium under the Insurance Policy for the Project. (ii) Dispute No. 2 Compensation for additional cost on account of Service Tax on the Bank Guarantee charges." 5. It was submitted by the respondent-claimant that in terms of Clause 21.1 of General Conditions of contract, for the works awarded under the contract, an insurance policy was required to be taken w.e.f. 1.4.2001 initially for a period to 13.09.2006 which was later extended to 30.09.2009. It was submitted that General In .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... payment of amounts under pars 6.1 & 6.2 above. No post award interest shall however be payable in case the above sums are payable within 90 days of the date of award." Similarly the Arbitral Tribunal awarded to the respondent-claimant following sums under dispute No. 2:- "10.1 The Claimant shall be paid by the Respondent an amount of Rs. 63,58,368/- on account of additional cost incurred on the Bank Guarantees furnished to the Respondent in terms of the Contract. 10.2 The Claimant shall also be paid by the Respondent a sum of Rs. 43,84,987/- towards interest on the above amount for period upto the date of this award i.e. 28.02.2013. 10.3 Post award interest shall be payable in addition on the awarded sum of Rs. 63,58,368/- at the ra .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... ppeal arising therefrom i.e. in FAO(OS)588 of 2013, the Division Bench of the High Court by its judgment and order dated 20.12.2013, which is presently under challenge, affirmed the view taken by Single Judge and dismissed the appeal. 8. The facts leading to the present appeal arising out of FAO(AS)590 of 2013 are more or less identical. In that matter identical claims were raised on two counts but arising out of a different contract by the very same claimant. The Arbitral Tribunal granted Rs. 8,84,969/- in respect of dispute no. 1 with interest @ 12% per annum under identical two heads as found in the earlier case. Similarly, in respect of dispute no.2, the Arbitral Tribunal awarded Rs. 42,35,385/- with interest @ 12% per annum. 9. In NH .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

..... ed to be given under the contract itself and such requirement was stipulated by the appellant primarily to reduce its financial risk and to bind the claimant for its performance or protecting the money advanced to the respondents. In his submission, furnishing a performance bank guarantee @ 10% of the contract price was a mandatory condition of the contract under Clauses 10.1 and 10.2 of COPA. Though at some stage the option of performance bond was mentioned in COPA, such option was withdrawn making performance security to be compulsorily in the form of an unconditional bank guarantee. Such requirement being directly referable to essential conditions and arising out of the terms of the Contract, according to him the matter was definitely wi .....

X X   X X   Extracts   X X   X X

→ Full Text of the Document

X X   X X   Extracts   X X   X X

 

 

 

 

Quick Updates:Latest Updates