Section 80IB deduction denied due to non-completion of project ...


Tax Deduction Denied for Project Delay and Size; Case Remanded for Compliance Check on Commercial Area Limits.

November 26, 2024

Case Laws     Income Tax     AT

Section 80IB deduction denied due to non-completion of project within stipulated period u/s 80IB(10) by 31.03.2008 and commercial construction exceeding limit under clause (d). Amendment via Finance Act 2004 from 01.04.2005 imposed new conditions for deduction for projects approved and commenced prior to 01.04.2005. Condition restricting commercial space is impossible if project at advanced stage per approved plan, but completion timeline reasonable with over three years allowed post amendment. Projects approved after 01.04.2005 also have four-year completion period. Issue of completion certificate requirement sub-judice before Supreme Court, remanded for fresh adjudication as per provisions at project approval, subject to judgments. Commercial area exceeding prescribed limit allowed if approved by local authority, verified against sanction plan. Matter remanded to assess commercial area conformity with approved plan. Appeals allowed for statistical purposes.

View Source

 


 

You may also like:

  1. Assessee's claim for foreign tax credit u/s 90 allowed despite delay in filing Form No. 67 after due date of filing return u/s 139(1). Delay in filing Form 67 cannot...

  2. Eligibility of Foreign tax credit - delay in compliance of a procedural provision - delay in filing Form No.67 - Assessee has vested right to claim the FTC under the tax...

  3. Deduction u/s 80IA was allowed despite delay in filing Form 10CCB due to technical glitches on the Income Tax portal. The form was filed 1 hour 22 minutes after the due...

  4. HC condoned a 35-day delay in filing GST appeal, emphasizing that procedural delays should not override substantive justice. The petitioner had demonstrated compliance...

  5. Rectification of mistake u/s 254 - Deduction u/s 80IB - Delay in filing of return of income (ITR) - The High Court, while acknowledging the belated filing of the ROI,...

  6. Tribunal found assessee had reasonable cause for delay in furnishing Tax Audit Report due to delay in finalization of statutory audit arising from dispute between Board...

  7. The HC allowed two writ petitions filed by a charitable trust seeking condonation of delay in filing Form 10-B for AYs 2014-15 and 2015-16, with delays of 3533 and 3198...

  8. The case pertains to the determination of the date of "purchase" for claiming deduction u/s 54F of the Income Tax Act. The issue revolves around whether the assessee has...

  9. Delay in filling appeal before ITAT - delay of 105 days - The Tribunal exercised its discretion in condoning the delay, emphasizing the importance of accepting...

  10. The AAR held that the GST rate for the project is governed by the one-time option exercised by the original promoter at 12% with input tax credit. The applicant is bound...

  11. Condonation of delay - Delay in filling of an appeal before ITAT - The ITAT observed taht the appeal was delayed by 17 days. The assessee claimed the delay was due to...

  12. Deduction u/s 80IA(4) - Disallowance of project facility expenses - Revenue expenses or Capital expenditure - Appellant was engaged in infrastructure development and...

  13. Condonation of delay beyond condonable period - appeal rejected on the sole ground that the appeal filed by the appellant is beyond the condonable period i.e., 56 days -...

  14. Condonation of Delay Scheme, 2018 - On day extension for compliance.

  15. Condonation of delay denied - Ignorance of law is no excuse - HC

 

Quick Updates:Latest Updates