Works contract or not - supply of solar rooftop power plant ...


Solar Rooftop Power Plant Supply Excluded from "Works Contract" Due to Immovable Property Exemption.

March 16, 2019

Case Laws     GST     AAR

Works contract or not - supply of solar rooftop power plant along with design, erection, commissioning & installation - the supplies under consideration are out of the ambit of “work contract” service in as much as the question of immovable property does not arise.

View Source

 


 

You may also like:

  1. The HC held that the supply of a Solar Power Generating System by the petitioner is a composite supply and does not amount to a works contract u/s 2(119) of the GST Act....

  2. Input tax credit - inputs / capital goods / input services - Solar Power Generating Plant of the applicant qualify as 'plant and machinery' as it falls under machinery -...

  3. Composite supply - natural bundling - The supply of the PV module which is the major component of the Solar Power Plant is not naturally bundled with the supply of the...

  4. Classification of supply - supply of services or not - works contract services - composite supply or not - the activities of installation, commissioning, testing,...

  5. Disallowance of higher reduction of depreciation on the cost of civil engineering works for laying foundation of solar power panels - the expenditure which is incurred...

  6. Classification of Service - Rate of GST - turnkey Engineering, Procurement and Construction (EPC) Contract for construction of a solar power plant - cannot be held as...

  7. Turnkey EPC Contract are not getting covered under supply of 'Solar Power Generating System' under Entry 234 of Schedule I of the Notification - The contract for...

  8. Classification of supply - composite supply or not - works contract service or not - contract involving supply of equipment / machinery & erection, installation&...

  9. The supply of goods along with design, erection, commissioning & installation of the same while supply of “solar rooftop power plant and solar irrigation water pumping...

  10. Rate of tax - Composite supply of Works Contract or not - supply of erection, commissioning and installation of ZLD plant along with O&M services for a period of 5 years...

  11. Composite supply of Works Contract - installation & commissioning of plant and machinery - supply of Pouch Filling Machine with online pouch coding machine of...

  12. Classification of supplies - works contract services - The contract for shifting of cables and replacing with underground cables can be classified as contract for...

  13. TDS u/s 194C - nature of composite contract - supply contract or works contract - supply of main plant at Chandrapur TPS extension project - Held as supply contract not...

  14. The AAR ruled that the applicant's generation and supply of electricity from their 10.2 MW solar power plant to TANGEDCO through grid constitutes a "supply" under GST...

  15. Classification of goods - rate of tax - Since the contract is an EPC contract, the activity carried out by the applicant is a composite supply of works contract as...

 